Section 75
00-02-0878
2013-03-07
- 44 -
If, for some reason, the engine cannot get the temperature below the temperature
setpoint in parameter 6214 within the time limit in parameter 6211, the engine will be
shut down by this timer. The reason for this could be high ambient temperature.
NOTE:
If the cooling-down timer is set to 0.0 s, the cooling-down
sequence will be infinite.
NOTE:
If the cooling-down temperature is set to 0 deg., the
cooling-down sequence will be entirely controlled by the timer.
Breaker Sequences
The breaker sequences will be activated depending on the selected mode:
Mode
Genset mode
Breaker control
Auto
All
Controlled by the unit
Manual
All
Push-button, M-Logic, Modbus, Digital input
Block
All
Controlled by the unit
Before closing the breakers, it must be checked that the voltage and frequency are OK.
Setpoints Related To MB Control
Parameter 7080 MB control.
Parameter 7081 Mode shift: When enabled, the EMS-GC10 will perform the AMF
sequence in case of a mains failure in load takeover or TEST mode
Parameter 7082 MB close delay: The time from GB OFF to MB ON
Parameter 7085 Load time: After opening of the breaker, the MB ON sequence will not
be initiated before this delay has expired. Please refer to the description of "Breaker
spring load time".
NOTE:
If no MB is configured and used, the relays and inputs
normally used for MB control become configurable.
NOTE:
The GB can only be closed if the mains breaker is open.
The MB can only be closed if the generator breaker is open.
Summary of Contents for EMS-GC10
Page 1: ...00 02 0878 Section 75 2013 03 07 GensetControllerUnit ModelEMS GC10 Operator sManual ...
Page 14: ...Section 75 00 02 0878 2013 03 07 8 Menu Structure Diagram ...
Page 33: ...Section 75 00 02 0878 2013 03 07 27 MB Open Sequence ...
Page 34: ...Section 75 00 02 0878 2013 03 07 28 GB Open Sequence ...
Page 35: ...Section 75 00 02 0878 2013 03 07 29 Stop Sequence ...
Page 36: ...Section 75 00 02 0878 2013 03 07 30 Start Sequence ...
Page 37: ...Section 75 00 02 0878 2013 03 07 31 MB Close Sequence ...
Page 38: ...Section 75 00 02 0878 2013 03 07 32 GB Close Sequence ...
Page 39: ...Section 75 00 02 0878 2013 03 07 33 Load Takeover LTO ...
Page 40: ...Section 75 00 02 0878 2013 03 07 34 Island Operation ...
Page 41: ...Section 75 00 02 0878 2013 03 07 35 Automatic Mains Failure AMF ...
Page 42: ...Section 75 00 02 0878 2013 03 07 36 Test Sequence ...
Page 48: ...Section 75 00 02 0878 2013 03 07 42 Stop Sequence The drawings illustrate the stop sequence ...
Page 74: ...Section 75 00 02 0878 2013 03 07 68 Start ...