4.2.8 Timing to Supply Power
(1) Timing to Supply Power
Supply power to RCON after power is supplied to SCON.
(2) Timing to Power Supply (when not in time for initial communication)
If the timing to supply power to SCON is later than to RCON (cannot make it in time for initial
communication), it is available to set the initial communication start delay in the gateway
parameter setting tool.
* When the startup of SCON could not be made in time for initial communication, in consistency
in number of axes (gateway error) could occur.
<Setting Item of Gateway Parameters>
Refer to 3.9 Gateway Parameter Setting Tool in RCON Instruction Manual
Value [ms]
Category
Name
Initial Value
Input Range
GW Parameters (3)
Standby Time for Initial Internal
Communication
0
0 to 65535
<Power Supply Sequence>
SCON Power Supply
(AC100/200V)
<Total Frame Communication>
Initial Communication
(Configuration Communication)
RCON Power Supply
(DC24V)
Delay setting is available in
gateway parameter setting tool
Cannot make it in time for
initial communication
<Power Supply Sequence>
SCON Power Supply
(AC100/200V)
<Total Frame Communication>
Initial Communication
(Configuration Communication)
RCON Power Supply
(DC24V)
Summary of Contents for SCON-CB-F
Page 2: ......
Page 4: ......
Page 10: ......
Page 16: ......
Page 48: ...1 Specifications Check 32 1 3 3 SCON CGB 3000W and above ...
Page 60: ...1 Specifications Check 44 ...
Page 266: ...3 Operation 250 ...
Page 276: ...4 Field Network 260 ...
Page 282: ...5 Vibration Suppress Control Function 266 ...
Page 362: ...9 Troubleshooting 346 ...
Page 444: ...10 Appendix 428 ...
Page 449: ......