b) Set
Specify Time Between Recurring Runs
to
0
days
,
0
hours
, and
0
minutes
.
Set up SMV automatic execution using ProLink III
Procedure
1. Select one of the following paths to access the SMV scheduler .
•
Choose
Device Tools
>
Diagnostics
>
Meter Verification
>
Meter Verification Scheduler
.
•
Choose
Smart Meter Verification Overview
>
Tools
>
Schedule Smart Meter Verification
.
2. To schedule a single test:
a) Set
Specify Time Until Next Run
to the number of days, hours, and minutes to elapse before the
test is run.
b) Set
Specify Time Between Recurring Runs
to
0
days
,
0
hours
, and
0
minutes
.
3. To schedule a recurring execution:
a) Set
Specify Time Until Next Run
to the number of days, hours, and minutes to elapse before the
first test is run.
b) Set
Specify Time Between Recurring Runs
to the number of days, hours, and minutes to elapse
between runs.
4. To disable scheduled execution:
a) Set
Specify Time Until Next Run
to
0
days
,
0
hours
, and
0
minutes
.
b) Set
Specify Time Between Recurring Runs
to
0
days
,
0
hours
, and
0
minutes
.
Set up SMV automatic execution using the Field Communicator
Procedure
1. Choose
Service Tools
>
Maintenance
>
Routine Maintenance
>
SMV
>
Automatic Verification
.
2. To schedule a single test:
a) Set
Hours Until Next Run
to the number of hours to elapse before the test is run.
b) Set
Recurring Hours
to
0
.
3. To schedule a recurring execution:
a) Set
Specify Time Until Next Run
to the number of days, hours, and minutes to elapse before the
first test is run.
b) Set
Specify Time Between Recurring Runs
to the number of days, hours, and minutes to elapse
between runs.
4. To disable scheduled execution:
a) Set
Specify Time Until Next Run
to
0
days
,
0
hours
, and
0
minutes
.
b) Set
Specify Time Between Recurring Runs
to
0
days
,
0
hours
, and
0
minutes
.
Configuration and Use Manual
Measurement support
MMI-20025166
March 2019
Configuration and Use Manual
205