Chapter 10: Web Interface Readings and Parameter Settings
10.6 Settings
10.6.1 Meter
General Setting
The basic metering configurations needed to set up the meter can be applied from the web
interface by clicking on Settings and selecting the 'Meter' tab. On the metering tab users
will see the 'General' tab selected and the page presented. The general page include the
following settings:
Device Description: A description for the meter can be provided in this field which will dis-
play on the Dashboard page.
Voltage Wiring: Select the type of wiring that the meter will be monitoring from the modes
in the drop down list.
Current Wiring: Select the number of CT's that will be connected to the meter to measure
the current.
PT1: Enter the rated input of the potential transformer that is connected to the meter. Pos-
sible range is from 50 to 1,000,000V. By default PT1 is 400.
PT2: Enter the rated output of the potential transformer. Possible range is from 50 to 400V.
The default PT2 setting is 400.
NOTE: If the voltage input is connected directly to the meter and there are no PTs (Potential
Transformers) stepping down the voltage to the meters voltage input then the PT1 and PT2
settings can be left as the default of 400.