4 - INSTALLATION
EN
Pag.
4/53
- Cap.
4
THIS MANUAL IS PROPERTY OF SCM INDUSTRIA S.P.A - ANY TOTAL OR PARTIAL REPRODUCTION IS STRICTLY FORBIDDEN
4.1
UNLOADING THE MACHINE
(ev_4-1_0.0)
NOTE-INFORMATION:
the packing of the machine indicates:
- the weight to be raised
- the hooking areas
DANGER-WARNING:
lifting and handling should only be carried out by skilled personnel specially trained to execute this
kind of operations. During loading and unloading, avoid knocks to prevent damages to persons or
things. Make sure no one is standing under the overhung load and/or within the bridge crane
working range during machine lifting and handling.
Before unloading the machine take off all parts rested on it for packing and transport reasons.
DANGER-WARNING:
- the machine shall be lifted by crane or other raising means by hooking the slings as shown in fig.
4.1.
- Make sure that the crane, the slings as well as the fork truck are proper for lifting the machine.
If a bridge crane or a crane is available, proceed as follows:
– provide three slings (C fig. 4.1) of suitable length and capacity (belts minimum length 2000 mm);
– lift the slings and position them as is shown in the figure 4.1;
– fasten the slings to the bridge crane (D fig. 4.1) having adequate lifting power;
– move the bridge crane by small steps to allow the slings (C fig. 4.1) to settle, until optimum stability
conditions are reached;
– lift carefully and slowly, without causing the load to swing, and place the machine in the selected setting.
If hoisting is carried out with a lift truck A, proceed as follows:
– provide a fork lift truck (A fig. 4.1) having suitable carrying capacity;
– insert the forks (B fig. 4.1) as per the figure (keeping them alongside the two feet (E fig. 4.1) and check that
these protrude at least 15 cm from the rear part of the base.