SECTION 6 – OPERATIONAL TEST AND PLACE IN SERVICE
PAGE 6-2 REV. 0 2014-MAY-02
TABLE 6-1: PREPARATION – OPERATIONAL TEST (Continued)
CHECKFIRE 210
Detection and Actuation System
Detection Circuit #1 (and #2)
Before conducting OPERATIONAL TEST, install the Detec-
tion Circuit Tester (DCT) (Part No. 440097).
1. Remove the Detection Circuit EOL Device from detection
circuit.
2. Set DCT to “Normal” condition then install DCT.
Power Up (External or dual power only)
Before conducting the OPERATIONAL TEST, make certain
external power is properly connected to CHECKFIRE 210
System (see Section 5 – Installation and Programming, page
5-17).
• If 3 amp fuse is not installed for external power, follow
instructions in Section 5 – Installation and Programming,
page 5-17 (step 5).
• If using dual power install battery
1. Remove battery compartment cover.
2. Insert battery into battery well; align connector keyways
and connect battery pigtail with battery cable on the
ICM.
RED TO POSITIVE (+)
BATTERY POST
BLACK TO NEGATIVE (–)
BATTERY POST
INLINE FUSE
HOLDER
CONFIRM
CONNECTIONS
FOLLOw SECTION 5 – INSTALLATION
INSTRUCTIONS TO INSTALL FUSE
009173
BATTERY CABLE
BATTERY
PIGTAIL
009347
REMOVE DETECTION
CIRCUIT EOL DEVICE
SET DCT TO
“NORMAL”
AND INSTALL
009161
009287