SECTION 6 – OPERATIONAL TEST AND PLACE IN SERVICE
2014-MAY-02 REV. 0 PAGE 6-21
CHECKFIRE 210
Detection and Actuation System
10. If needed complete installation of optional pneumatic
manual actuator(s). Refer to Section 5 – Installation and
Programming.
11. Re-install pneumatic manual actuator cartridge(s) if previ-
ously removed.
12. Reconnect all power as required. Reconnect external
power circuit connection at the CHECKFIRE 210 ICM
Power receptacle. If internal battery is required, reconnect
ICM battery cable to battery pigtail.
13. Confirm system is clear of faults and alarm conditions.
14. Cancel Isolate mode by returning the Isolate switch to the
normal position.
15. Reset to Normal: Press and hold “DELAY/Reset/Silence”
button for 3 seconds; Green and Red LEDs are steady-on
for 1 second; then Amber LEDs are steady-on for 1
second; at end sounder quickly pulses 3 times.
16. Record results of testing. If desired, download Event
History Log, refer to Section 5 – Installation and Program-
ming, page 5-33 (manual) or 5-38 (PC). When complete
re-install battery cover.
TABLE 6-6: PLACING CHECKFIRE 210 SYSTEM IN SERVICE (Continued)
009171
ELECTRONIC ACTIVATION
INSTALLATION COMPLETE
IF REMOVED, RE-INSTALL
MANUAL ACTUATOR
CARTRIDGE(S)
RECONNECT ALL POWER
CONFIRM SYSTEM CLEAR
OF FAULTS AND/OR ALARM
CONDITIONS
REMOVE SYSTEM FROM
ISOLATE MODE
009290
RESET TO NORMAL
PRESS AND HOLD
3 SECONDS
POWER LED IS
GREEN STEADY-ON