5 Parts Replacement
Issue 02 (2016-11-15)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
45
2.
Remove the faulty pad power socket from the guide rails of the cabinet.
Step 2
Install the new pad power socket on the guide rails by referring to the preceding method, and
connect cables.
----End
5.2.7 Replacing a Modbus Card
Prerequisites
Tools: ESD gloves, Phillips screwdriver.
Materials: A spare Modbus card of the same model is available and functional.
Procedure
Step 1
Record positions where the signal cable connect to the Modbus card.
Step 2
Remove the Modbus card, and remark the DIP switch position.
Step 3
Set the DIP switch in new Modbus card base on the recorded information.
Step 4
Install a new Modbus card.
Step 5
Install the signal cables to the Modbus card base on the recorded information.
Step 6
Add UPS on the WebUI.
----End
5.2.8 Replacing an ATS Controller
Prerequisites
Tools: electroprobe, insulation gloves, Phillips screwdriver, multimeter.
Materials: A spare ATS controller of the same model is available and functional.
The ATS controller is damaged or faulty and cannot work.
The figures are for reference only. The actual product appearance prevails.
Procedure
Step 1
Open the front door of the Converged Cabinet.
Step 2
Remove the front panel from the ATS PDU using a Phillips screwdriver, as shown in