HDG Bavaria GmbH 07/2008
HDG Compact 99 - 200 - Version 1 - en
6 Using the heating system – ON/OFF menu
77
6.6 ON/OFF menu
P
ROCEDURE
1.
Press the
F1
key under the standard display screen.
✓
You are in the
ON/OFF
menu.
2.
Scroll with the
F1
or
F2
key to the previous or next submenu.
3.
Use the
F3
key under the
FIELD
command in the respective sub-
menu to select the desired parameter.
4.
Press the
F4
key under the
CHOOSE
command and select the
desired setting.
5.
Confirm each change with the
Enter
key.
✓
The desired parameter is set.
6.
Press the
F6
key under the
END
command to exit the submenu.
✓
The standard display is restored.
S
ETTING
THE
BASE
LOAD
/
PEAK
LOAD
BOILER
This menu can be used to integrate an additional peak load boiler
using a third accumulator temperature sensor. With a double hea-
ting system, both boilers store energy in the accumulator. If the base
load boiler cannot charge the accumulator by itself, the peak load
boiler switches on for support.
This menu allows you to configure which heating system will be the
base load boiler and the which will be the peak load boiler in a
double heating system. A changeover is required after a certain
amount of operating hours so that both boilers will have approxi-
mately the same number of operating hours over several years.
✎
See “Procedure” in this section.
This is an optional submenu and only available with double heating
systems.
Changeover base load/peak load
1-01
Base load
Peak load
Boiler-1
Boiler-2
After operating hours
:
0 /
0 hr
FIELD
CHOOSE
END