6 Using the heating system – TIME menu
96
HDG Compact 99 - 200 - Version 1 - en
©
HDG Bavaria GmbH 07/2008
S
ETTING
THE
CLEANING
FUNCTION
In this submenu you can set the time for the movements of the
cleaning system as well as scanning of the limit switch.
✎
See “Procedure” in this section.
S
ETTING
FILLING
DELAY
OF
DOSAGE
TANK
In this submenu you can set a time-delayed switching on for the silo
delivery system. If the fill level indicator in the dosage tank signals
that more fuel is required, the extraction switches back on after the
specified time has elapsed.
Time
3-03
Ash removal
runtime
:
12 /
0 s
Ash removal
pause time
:
70.0 / 0.0 m
Keep glow runtime
:
10 /
0 s
Keep glow pause time
:
10.0 / 0.0 m
END
When changing the heating material, the burn-out behaviour must
be checked on the grate of the boiler. If necessary, adjust the
Ash
removal pause
parameter. In general, only this parameter
should be changed and the
Ash removal feed
parameter only
changed in exceptional instances.
Time
3-04
Cleaning system pause time
:
24.0 / 0.0 h
Cleaning system runtime
:
140 /
0 m
Cleaning system monitoring
:
40 /
0 s
END
When changing the heating material, the burn-out behaviour of the
boiler must be checked in the area of the heat exchanger surfaces.
If necessary, adjust the
Cleaning pause time
parameter. In
general, only this parameter should be changed and the
Cleaning system runtime
parameter only changed in excep-
tional instances.
This parameter is an optional submenu and only available for hea-