HDG Bavaria GmbH 07/2008
HDG Compact 99 - 200 - Version 1 - en
5 Commissioning the system – Procedure
67
F
EEDING
,
METERING
AND
LATERAL
AUGER
In this submenu, the feeding and the transverse auger can optionally
be activated together with the dosing auger lying in between.
See chapter “6 Using the heating system”, section “6.9 MANUAL
menu”, paragraph “Feeding, metering and lateral auger”.
S
LIDING
TRAY
This submenu is used to manually activate the drive of the moving
floor (if installed).
✎
See chapter “6 Using the heating system”, section “6.9 MANUAL
menu”, paragraph “Moving floor”.
Once the functionality of all the actuators is checked in manual ope-
ration, the HDG Compact 99 - 200 heating system can be operated in
accordance with the set control mode.
F
ILLING
THE
ASH
ACCUMULATION
BIN
1.
When commissioning the system, make sure that both ash accu-
mulation bins (1) are at least half-filled with ash, sand, etc.
The following section is only relevant when operating theHDG
Compact 99 - 200 heating system with a central ash removal
system.
Caution!
Material damage and injury due to backfiring or smoke
If the ash accumulation bins are not at least half-filled when com-
missioning or re-starting after a cleaning, there is a danger of back-
firing or smoke from the boiler. This can cause damage to the
heating system or injury to persons.
Make sure that both ash accumulation bins are at least half-filled
with ash or sand.
Figure 5/1 - Filling the ash accumulation bin
1