4 Planning and installation – Installing the heating system
54
13.Install the drive motor (1) on the ash removal auger using the M8
screw (spanner size SW13) including the spring ring and washers.
14.Slide the ash bin (6) with the intermediary seal (5) onto the auger
trough (4).
15.Secure the ash bin (6) using the star-grip screws (3).
✓
The central ash removal system is now installed.
F
ITTING
THE
BUFFER
PROBE
✓
The sensors are installed.
Caution!
Material damage and injury due to burn-back or smoke
If the ash accumulating bins are not at least half-filled when com-
missioning or re-starting after a cleaning, there is a danger of back-
firing or smoke from the boiler. This can cause damage to the
heating system or injury to persons.
Make sure that both ash accumulation bins (1) are at least half-filled
with ash, sand, etc.
The sensors for the buffer tank are in the EMD-C 215 Exclusiv control
cabinet for further use.
1. Seal the immersion sleeves of
the sensors with a suitable
sealing material and position
them at the points indicated
in the figure 4/25.
2. Guide the sensors into the im-
mersion sleeves.
3. Insert the prefabricated plug
connections into the termi-
nals specified in the circuit
diagram.
Figure 4/25 - Installing the sensors
1
For a hydraulic diagram without buffer tank, these sensors are not
present and must be taken out of the corresponding parameters.