4 Planning and installation – Installing the heating system
47
P
LACING
THE
BOILER
T
RANSPORT
There are several options for transporting the HDG Compact 99 - 200
boiler. It can be performed with a crane, forklift or a lifting truck.
I
NSTALLATION
SITE
1. Transport the boiler using suitable lifting equipment.
2. Place the boiler at the planned location while observing the mi-
nimum clearances.
✎
See section “4.1 Planning the heating system”, paragraph “Re-
quired room sizes and minimum spacing” in this chapter.
3. Align the boiler with plastic plates or flat steel strips (not included
in the scope of delivery) so that it is horizontal.
4. Unscrew the ring bolt from the boiler.
✓
The boiler has been set up.
I
NSTALLING
THE
FEEDING
SYSTEM
A
TTACHING
THE
ADAPTER
PIPE
1. Slide the adapter pipe (1) with the seal (3) into the
feed channel (4).
2. Align the seal (3) with the holes.
3. Poke a hole through the seal (3) for the centring screw (2).
Warning!
Danger from suspended loads
The boiler weighs over 1000 kg. If the boiler is dropped during
transport, persons can be seriously injured and the boiler can be da-
maged.
Make sure that you use appropriate lifting gear when placing the
boiler.
Ensure that the chain hoist is correctly secured to the eyebolt of the
boiler during crane transport of the heating system.
Figure 4/13 - Attaching the adapter pipe
4
1
3
2