Gree GMV6 HR DC Inverter VRF Units Service Manual
18
3.1.3 Checking
NOTE!
Items not complying with installation specifications need to be recorded in time as analysis basis for
the test of the refrigerating system.
Checklist before commissioning
Checklist Before GMV6 HR Commissioning
Category
No.
Item
Reference Value
Qualified
Inspector
Installation
drawings
1
Are the engineering design
drawings complete?
—
2
Is the project constructed according
to the design drawings?
—
Installation
environment
3
Is there any pollution source in the
outdoor unit installation
environment, and is the outdoor unit
installation location selected
correctly?
Refer to the outdoor unit
installation.
4
Is the outdoor unit foundation firm?
Do vibration reduction and drainage
meet the requirements?
Refer to the outdoor unit
installation.
5
Are the outdoor unit basic modules
installed at the same level?
Refer to the outdoor unit
installation.
6
Does the outdoor unit operate with
static pressure? Is the
corresponding static pressure set?
—
7
Is the hydro box installation location
selected correctly?
Refer to the hydro box
installation manual.
8
Is the mode exchange box unit
installation location selected
correctly?
Refer to the mode exchange
box installation manual.
Refrigerating
system
9
Is the rated capacity of the internal
and external units of the cooling
system within 50%~135%?
50% to 135%
10
If the single cooling system hydro
box and the rated capacity of
outdoor unit meet the requirements
of instruction manual?
Refer to the hydro box
installation manual.
11
Is the fresh air unit access capacity
within 30%?
≤30%
12
Is GMV6HR connected to outdoor
units in other series?
GMV6 HR cannot be
connected to outdoor units in
other series.
13
Does the drop between the indoor
and outdoor units meet the unit
design requirements?
Refer to the outdoor unit
installation.
14
Does the drop between indoor units
meet the unit design requirements?
Refer to the outdoor unit
installation.
15
Is the length of the pipe from the
outdoor unit to the farthest indoor
unit less than or equal to 200 m?
Refer to the outdoor unit
installation.
16
Is the total length of the piping less
than 1000 m?
Refer to the outdoor unit
installation.
17
Is the length of the outdoor unit to
the first branch joint greater than 90
m? If yes, is the pipe diameter
increased accordingly?
The pipe diameter needs to
be increased when the
length is greater than 90 m.
Summary of Contents for GMVVQ1015WM/C-X
Page 418: ...Gree GMV6 HR DC Inverter VRF Units Service Manual 416 GMV VQ400WM C X GMV VQ450WM C X...
Page 420: ...Gree GMV6 HR DC Inverter VRF Units Service Manual 418 NCHS1D...
Page 421: ...Gree GMV6 HR DC Inverter VRF Units Service Manual 419 NCHS2D...
Page 422: ...Gree GMV6 HR DC Inverter VRF Units Service Manual 420 NCHS4D...
Page 423: ...Gree GMV6 HR DC Inverter VRF Units Service Manual 421 NCHS8D...
Page 426: ...Gree GMV6 HR DC Inverter VRF Units Service Manual 424 6 1 2 Heating Operation...
Page 427: ...Gree GMV6 HR DC Inverter VRF Units Service Manual 425 6 1 3 Main body Cooling...
Page 428: ...Gree GMV6 HR DC Inverter VRF Units Service Manual 426 6 1 4 Main body Heating...
Page 430: ...Gree GMV6 HR DC Inverter VRF Units Service Manual 428 6 2 2 Heating Operation...
Page 431: ...Gree GMV6 HR DC Inverter VRF Units Service Manual 429 6 2 3 Main body Cooling...
Page 432: ...Gree GMV6 HR DC Inverter VRF Units Service Manual 430 6 2 4 Main body Heating...
Page 433: ...JF00304244...