To adjust the system height (lowest height) configuration
1. Remove the side panels from the unit.
2. If not already configured for the lowest position, use a forklift to raise the unit 0.5–1 meter
(2–3 feet) off the floor.
3. Remove the two M8 screws that secure the plate and foot assembly to the frame.
4. Remove the leveling foot from the block.
5. Orient the block in the cylinder facing upward and the flat foot is down.
Figure 16.
Changing Leveling Foot
6. Reassemble the foot assembly onto the frame.
7. To adjust the leveling feet, loosen the locking nut with a wrench and then turn the
adjustment nut.
●
Turn the nut clockwise to raise the unit
●
Turn the nut counter-clockwise to lower the unit
Figure 17.
Leveling Foot
8. Use a level or machine height measurements to make sure that the system is level.
9. Manually slide a panel through the incoming and outgoing conveyor sections to make sure
that the SE500
ULTRA
conveyor rail is properly aligned. The panel should pass from the
upstream conveyor through the SE500
ULTRA
and on to the downstream conveyor without any
resistance.
10. After adjusting the leveling feet, tighten the locking nuts.
Leveling foot block oriented
for standard configuration
Leveling foot block
oriented for lowest
conveyor position
Machine frame
Leveling foot
M8 Screws
Locking nut
Adjustment nut
Summary of Contents for SE500ULTRA
Page 1: ...SE500ULTRA Hardware Manual ...
Page 6: ...Contents vi SE500ULTRA Hardware Manual ...
Page 10: ...x SE500ULTRA Hardware Manual This page is intentionally left blank ...
Page 28: ...Chapter 1 System Overview 18 SE500ULTRA Hardware Manual Dimensions Figure 8 Front View ...
Page 30: ...Chapter 1 System Overview 20 SE500ULTRA Hardware Manual ...
Page 184: ...Chapter 5 System Drawings 174 CyberOptics Corporation ...