When different length of main boom is required, crane operator only needs to disconnect main
boom pivot section from main boom head, and then install main boom intermediate sections
between them. In this way, main boom can be assembled to required length. The assembly of
main boom from 42'8" (13m) to 219'10" (67m) is shown in the table 5-8.
Table 5-8 Assembly of main boom
Main boom
length
Assembly sequence of
main boom sections
Main boom
length
Assembly sequence of main boom
sections
42'8"(13m)
G11+G12
141'1"(43m)
G11+G13+3×G15+G12
52'6"(16m)
G11+G13+G12
150'11"(46m)
G11+G14+3×G15+G12
62'4"(19m)
G11+G14+G12
160'9"(49m)
G11+G13+G14+3×G15+G12
72'2"(22m)
G11+G15+G12
170'7"(52m)
G11+G13+4×G15+G12
82'(25m)
G11+G13+G15+G12
180'5"(55m)
G11+G14+4×G15+G12
91'10"(28m)
G11+G14+G15+G12
190'4"(58m)
G11+G13+G14+4×G15+G12
101'9"(31m)
G11+G13+G14+G15+G12
200'2"(61m)
G11+G13+3×G15+G15A+G15+G12
111'7"(34m)
G11+G13+2×G15+G12
210'(64m)
G11+G14+3×G15+G15A+G15+G12
121'5"(37m)
G11+G14+2×G15+G12
219'10"(67m)
G11+G13+G14+3×G15+G15A+G15+G12
131'3"(40m)
G11+G13+G14+2×G15+G12
DANGER
(1) Principle for assembling main boom: when connecting main boom intermediate
sections to main boom pivot section, always bolt the shorter intermediate sections
first.
(2) The combination of 219'10" (67m) main boom in above table is preferable
combination.
(3) The tip boom can be assembled on main boom mentioned above, except for 210'
(64m) and 219'10" (67m) main boom.
(4) Intermediate tensioner must be fitted on 210' (64m) and 219'10" (67m) main boom.
For reference only.
Operators manual should be consulted and adhered to.
Содержание ZCC1100
Страница 2: ...For reference only Operators manual should be consulted and adhered to...
Страница 4: ...For reference only Operators manual should be consulted and adhered to...
Страница 6: ...For reference only Operators manual should be consulted and adhered to...
Страница 12: ...For reference only Operators manual should be consulted and adhered to...
Страница 14: ...For reference only Operators manual should be consulted and adhered to...
Страница 22: ...For reference only Operators manual should be consulted and adhered to...
Страница 80: ...For reference only Operators manual should be consulted and adhered to...
Страница 82: ...For reference only Operators manual should be consulted and adhered to...
Страница 140: ...For reference only Operators manual should be consulted and adhered to...
Страница 206: ...For reference only Operators manual should be consulted and adhered to...