28
ABB
4 ABB
4.1 ABB PVS300/800
Termination
Addressing
Interface
Yes
Yes
RS485
Select “ABB: PVS Central” during the inverter detection.
Overview
•
Where to connect: X4 terminal block under the cover.
•
Communication address must be allocated.
•
3-pin wiring.
•
Installation steps:
•
Switch off the inverters and Solar-Log™.
•
Connect inverters to the Solar-Log™.
•
Connect the inverters to each other.
Connect inverters to the Solar-Log™
The wiring is done using a
•
self-made cable connection with terminal block connector.
Procedure
1. Unscrew the side cover as shown in the inverter's instructions.
2. If you are making the cable yourself, connect the wires as shown in the following diagram:
Solar-Log™ terminal strip connector
X4 terminal block inverter
Terminal
PIN
►
1
►
1 - Data+
►
3
►
3 - GND
►
4
►
2 - Data-
3. If no further inverter is connected, terminate the inverter according to the instructions for the inverter.
4. Screw the inverter cover on again.
5. Insert the terminal block connector into the Solar-Log™ RS485 socket.
Connect the inverters to each other
•
Where to connect: X4 terminal block under the cover.
Summary of Contents for Solar-Log
Page 1: ...1 Components Connection Manual V 4 2 3 Solar Log EN ...
Page 20: ...20 01 Inverter ...
Page 398: ...398 Appendix 113Appendix 113 1 SMA mixed wiring Fig SMA mixed wiring ...
Page 402: ...402 02 Meter ...
Page 444: ...444 03 Battery Systems ...
Page 456: ...456 sonnen Note Only one battery system can be connected to a Solar Log device ...
Page 463: ...463 04 Heating rods ...
Page 470: ...470 05 Heating pumps ...
Page 478: ...478 06 Sensors ...
Page 488: ...488 07 Pyranometer ...
Page 495: ...495 08 Smart Plug components ...
Page 502: ...502 09 Power Charging Stations ...