253
SAJ
73
SAJ
73.1 Suntrio
Termination
Addressing
Interface
-
Yes
RS485
Select „SAJ“ during the inverter detection.
Supported models (as of firmware 4.2.1):
•
4K-60K
Overview
•
Integrated interface.
•
Where to connect: Round sockets on the outside of the inverter.
•
3-pin wiring.
•
Communication address must be allocated.
•
Installation steps:
•
Switch off the inverters and Solar-Log™.
•
Connect inverters to the Solar-Log™.
•
Connect the inverters to each other.
•
Allocate communication address.
Connect inverters to the Solar-Log™
The wiring is done using a
•
self-made, shielded 3 wire data cable with round plug and terminal block connector.
Procedure
1. If you are making the cable yourself, connect the wires as shown in the following diagram:
Solar-Log™ terminal strip connector
Inverter round socket
Terminal
PIN
►
1 Data+
►
PIN A
►
3 GND
►
GND
►
4 Data-
►
PIN B
2. Insert the round plug into any COM round socket on the inverter.
3. Insert the terminal block connector into the Solar-Log™ RS485 socket.
Connect the inverters to each other
•
Wiring using 3 pin cable with round plugs.
•
Where to connect: Round sockets on the outside of the inverter.
Summary of Contents for Solar-Log
Page 1: ...1 Components Connection Manual V 4 2 3 Solar Log EN ...
Page 20: ...20 01 Inverter ...
Page 398: ...398 Appendix 113Appendix 113 1 SMA mixed wiring Fig SMA mixed wiring ...
Page 402: ...402 02 Meter ...
Page 444: ...444 03 Battery Systems ...
Page 456: ...456 sonnen Note Only one battery system can be connected to a Solar Log device ...
Page 463: ...463 04 Heating rods ...
Page 470: ...470 05 Heating pumps ...
Page 478: ...478 06 Sensors ...
Page 488: ...488 07 Pyranometer ...
Page 495: ...495 08 Smart Plug components ...
Page 502: ...502 09 Power Charging Stations ...