VII. Commissioning
1. Important Checks before the Commissioning
● If there is any wrong connected wires? Pay special attention to the
terminal of U.V.W; Make sure the power supply wires are connected
to R.S.T, not U.V.W.
● If there is any metal powder or wires left on the base plate of the
inverter or the terminal block, which may cause short circuit.
● If screws are tightly locked and if the connecting parts are loose.
● If there is any short circuit or earth fault at outputs.
2. Commissioning Methods
The procedure of the operator is factory set up for the control mode of
HLP series. The commissioning can be carried out through the digital
operator. Generally, the commissioning can be conducted at 5.00 Hz.
Note: ¤means indicator is on;
means indicator lamps flash;
0
mean
digits flash.
Procedures
Display
Indicator Lamp
Explanation
Power up
↓
←
Dsp2.0
AXX.XX
FWD Hz
¤
Self detect when power-
up, display version
no. display running
frequency
↓
▲
00.0
0
FWD Hz
¤
Switch to adjustable
frequency
↓
← ▲
0
5
.00
FWD Hz
¤
Display the content of
CD000
↓
ENTER
05.00
FWD Hz
¤
Change the content of
CD000.confirm the
value
↓
RUN
05.00
FWD Hz
¤ ¤
Running at 5.00Hz
↓
STOP
05.00 (flash)
FWD Hz
¤
Stop
Summary of Contents for HLP-A Series
Page 1: ......
Page 2: ...HLP A Series...
Page 3: ......
Page 27: ...HLP A Series HLP A Series 22 1 Good 2 Good 3 Not good...
Page 69: ...HLP A Series HLP A Series 64 The following is the block diagram of multi pumps operation...
Page 106: ...HLP A Series HLP A Series 101 HLPA05D523B HLPA07D523B Unit mm HLPA05D543B HLPA07D543B Unit mm...
Page 117: ......