5 - 10
Testing and Fault Finding
K0260 Issue No. 8
Key-pad Testing
The front panel key-pad and the hand terminal key-pad can be tested using the facility in the
maintenance/calibration selection of the set-up menu.
The procedure to test the key-pad requires each key to be pressed in turn and to confirm the
correct key press on the display. Make sure the display shows only the appropriate key press.
Note:
Connecting the hand terminal disables the front panel key-pad.
F
IGURE
5-4 K
EY
-
PAD
T
EST
D
ISPLAY
Summary of Contents for Druck ADTS 505
Page 1: ...GE Measurement Control Druck ADTS 505 Air Data Test Set User Manual K0260 ...
Page 14: ...xii K0260 Issue No 8 Druck ADTS 505 User Manual ...
Page 54: ...3 26 Operation K0260 Issue No 8 ...
Page 55: ...Druck ADTS 505 User Manual 3 27 K0260 Issue No 8 3 ...
Page 56: ...3 28 Operation K0260 Issue No 8 ...
Page 66: ...5 4 Testing and Fault Finding K0260 Issue No 8 FIGURE 5 1 FAULT FINDING CHART ...
Page 80: ...5 18 Testing and Fault Finding K0260 Issue No 8 Intentionally left blank ...
Page 124: ...6 44 Reference and Specification K0260 Issue No 8 Intentionally left blank ...