5. Carefully fit the antenna into the still-pipe.
$
'
&
(
%
A. Closing
B. Align mark with notch on the pipe flange
C. Still-pipe flange
D. Notch that indicates direction of the Verification Pin
E. Nozzle
6. Direct the closing so that the mark aligns with the notch on the pipe flange.
7. Tighten the closing onto the still-pipe flange (customer supplied screws and nuts).
The tank is now sealed and can, as far as Rosemount Tank Gauging equipment is
concerned, be pressurized.
Note
For a safe installation on a pressurized tank it is important that the gauge is installed
in accordance with the appropriate local, national, and international standards,
codes, and practices.
8. Remove the protection cap from the waveguide.
A
A. Protection cap
Installation
Reference Manual
September 2019
00809-0100-5901
100
Reference Manual
Summary of Contents for Rosemount 5900C
Page 1: ...Reference Manual 00809 0100 5901 Rev DA September 2019 Rosemount 5900C Radar Level Gauge ...
Page 6: ...Contents Reference Manual September 2019 00809 0100 5901 vi Reference Manual ...
Page 12: ...Introduction Reference Manual September 2019 00809 0100 5901 12 Reference Manual ...
Page 116: ...Installation Reference Manual September 2019 00809 0100 5901 116 Reference Manual ...
Page 204: ...Configuration Reference Manual September 2019 00809 0100 5901 204 Reference Manual ...
Page 208: ...Operation Reference Manual September 2019 00809 0100 5901 208 Reference Manual ...
Page 290: ...Product Certifications Reference Manual September 2019 00809 0100 5901 290 Reference Manual ...