REYQ8~20+REMQ5U7Y1B
VRV IV+ Heat Recovery
ESIE18-15B – 2020.05
3
Check the power supply to the unit, see
356].
Does the Unit receive power?
Action
Yes
Correct the wiring from the main power
supply terminal to the Branch selector
box PCB, see
361].
No
Adjust the power supply to the unit, see
To check the HAP LED of the branch selector box PCB
Prerequisite:
First perform a power check of the Branch selector box PCB, see
1
Locate the HAP LED on the Branch selector box PCB.
BS1Q-A
a
a
HAP LED
BS4~16Q-A
a
a
HAP LED
Does the HAP LED blink in regular
intervals (approximately 1 Hz)?
Action
Yes
Return to
214] of the Branch
selector box PCB and continue with the
next procedure.
No
Replace the Branch selector box PCB,
see
217].