Dionex ICS-5000
+
Installation Instructions
114
Doc. 065447-02 12/14
5. Open the DC upper door and route the line from the separator column
outlet through the tubing slot to the upper compartment of the DC.
Plumbing the Suppressor and Conductivity Cell in the DC
1. Hydrate the suppressor. Refer to the suppressor manual for the
recommended number of backpressure coils.
2. Connect the tubing to the suppressor and cell as shown in
.
3. Close the DC door.
4. Go on to system equilibration (
Plumbing the Electrochemical Cell in the DC
1. Before completing the electrochemical cell plumbing, follow the
instructions in
to install the cell electrodes and the cell inlet
tubing.
2. Connect the tubing to the cell as shown in
3. Place the waste line from the cell out port into a waste container or
appropriate drain.
4. Close the DC door.
5. Go on to system equilibration (
4.2.9
Plumbing the TC for Analytical IC Applications
Plumbing the TC Injection Valve and Columns
1. Before connecting the columns, pump eluent through the columns to
waste for at least 30 minutes as described in the column manual. Pump at
the standard flow rate for the column. For detailed column startup and
operational instructions, refer to the column manual provided on the
Thermo Scientific Reference Library DVD (P/N 053891).
2. Locate these items in the TC Ship Kit (P/N 064789):
For correct drainage, make sure waste lines are not bent, pinched, or
elevated at any point. Do not allow the ends of the lines to be
submerged in waste liquid.