51V Voltage Dependent Overcurrent – Phase
OC Phase
Control Voltage
CT1(I
A
)
V
12
(V
AB
)
CT2(I
B
)
V
23
(V
BC
)
CT3(I
C
)
V
31
(V
CA
)
IDMT Phase Overcurren
t elements 51-n should be tested for pick-up and timing before this function is
tested. The
General Pickup
LED can be used to assess operation of this function if other functions are disa-
bled or if the setting allocating
General Pickup
is temporarily modified.
Apply nominal 3 phase balanced voltage. Apply 3 phase balanced current at a level below the normal 51-n
setting but above the effective 51V-n setting. Ensure that the thermal rating of the relay is not exceeded.
Gradually reduce the voltage until the a-b voltage is less than the
Voltage
setting.
Pickup
LED operation
can be used to confirm the
Voltage
setting. If the 51V-n current setting is above the continuous rating of the
relay an alternative procedure should be used, apply test current in short duration shots with applied voltage
being gradually reduced for each subsequent shot.
Apply nominal 3 phase balanced voltage. Increase the voltage such that the a-b voltage is 110 % of the
Voltage
setting. Test current can be applied as 3 phase balanced current or as a single phase a-b current via
CT1 and returning through CT2. Gradually increase the a-b phase current or balanced 3P current until
Pickup
LED operates. Confirm result of phase O/C test above.
Reduce the applied voltage to a level such that VAB phase-phase voltage is less than 90 % of the setting. The
element threshold is operated by phase to phase voltage but the most common connection of the 3 phase
voltage inputs is phase to neutral.
Gradually increase the CT1 phase-phase current until
Pickup
LED operates.
Note that these elements may be set as directional. If this is the case, the phase angle of the current must be
set with respect to the voltage to produce operation of the elements.
Voltage Setting (V, p-p)
Measured (V, p-p)
I Setting
Multiplier
Calculated PU
Measured
Tolerance
51-1 Pickup
51-2 Pickup
51-3 Pickup
51-4 Pickup
Element Blocking
The
Voltage Controlled Overcurrent
function can be set to Inhibit for
VT Supervision
operation.
This functionality should be checked. Apply balanced voltage and current. Reduce a-phase voltage to cause a
VTS condition. Increase 3P current until the element operates at its full setting, i.e. 51V settings are not used.
Element
VTS Action
51-1
51-2
51-3
51-4
Check correct indication, trip output, alarm contacts.
9.10.15
Functional Tests
9.10 Protection Functional Tests
440
Reyrolle 7SR5, Transformer Protection Device, Device Manual
C53000-G7040-C015-1, Edition 11.2019
Содержание Reyrolle 7SR5
Страница 8: ...8 Reyrolle 7SR5 Transformer Protection Device Device Manual C53000 G7040 C015 1 Edition 11 2019 ...
Страница 24: ...24 Reyrolle 7SR5 Transformer Protection Device Device Manual C53000 G7040 C015 1 Edition 11 2019 ...
Страница 132: ...132 Reyrolle 7SR5 Transformer Protection Device Device Manual C53000 G7040 C015 1 Edition 11 2019 ...
Страница 142: ...142 Reyrolle 7SR5 Transformer Protection Device Device Manual C53000 G7040 C015 1 Edition 11 2019 ...
Страница 338: ...338 Reyrolle 7SR5 Transformer Protection Device Device Manual C53000 G7040 C015 1 Edition 11 2019 ...