[dw_7SR5_function81SettingExample, 1, en_US]
•
First stage
Least important load such as domestic customers.
•
Second stage
Separate stage load such as further domestic load and infrastructure supply.
•
Third stage
Light industrial customer load.
•
Fourth stage
Higher importance light industrial load.
•
Unaffected loads
Critical load which should be maintained whenever possible.
Settings for timings should be assessed depending on network requirements and customer practices.
Frequency setting should avoid expected network variations. Timing should allow for system fault detection
and clearance. Timing between stages should allow for CB operation and system recovery following shedding
of previous stage.
Element
Setting Values
81-1
81-1 Element
Enabled
81-1
81-1 Operation
Under
81-1
81-1 Setting
49.5 Hz
81-1
81-1 Hysteresis
0.1 %
81-1
81-1 Delay
3 s
81-1
81-1 Input Selection
VT1/2/3
81-2
81-2 Element
Enabled
81-2
81-2 Operation
Under
81-2
81-2 Setting
49.5 Hz
81-2
81-2 Hysteresis
0.1 %
81-2
81-2 Delay
5 s
81-2
81-2 Input Selection
VT1/2/3
81-3
81-3 Element
Enabled
81-3
81-3 Operation
Under
81-3
81-3 Setting
49.2 Hz
Protection and Automation Functions
5.20 81 Frequency Protection – "f>" or "f<"
Reyrolle 7SR5, Transformer Protection Device, Device Manual
291
C53000-G7040-C015-1, Edition 11.2019
Содержание Reyrolle 7SR5
Страница 8: ...8 Reyrolle 7SR5 Transformer Protection Device Device Manual C53000 G7040 C015 1 Edition 11 2019 ...
Страница 24: ...24 Reyrolle 7SR5 Transformer Protection Device Device Manual C53000 G7040 C015 1 Edition 11 2019 ...
Страница 132: ...132 Reyrolle 7SR5 Transformer Protection Device Device Manual C53000 G7040 C015 1 Edition 11 2019 ...
Страница 142: ...142 Reyrolle 7SR5 Transformer Protection Device Device Manual C53000 G7040 C015 1 Edition 11 2019 ...
Страница 338: ...338 Reyrolle 7SR5 Transformer Protection Device Device Manual C53000 G7040 C015 1 Edition 11 2019 ...