Microprocessor Controller
62
Sequence Of Operation
Unit Start-up
A 60 second sequence start of the required loads occurs during initial start-up of the controller. If cooling
is required, the unit operates in the cool mode until the controlling sensor reaches 1.0 C (1.8 F) below
setpoint.
•
When the unit On/Off switch is turned ON, the LED display turns On and then Off.
•
The setpoint appears briefly in the LED display.
NOTE: When the setpoint appears in the LED display, both the Return and Supply LEDs are lit.
•
The LED then shows the controlling air sensor temperature.
•
The controller senses the incoming power phase and selects the correct power phase to unit
components.
•
The evaporator fan motors start. Evaporator fans operate continuously in low speed.
•
The R-134a compressor and condenser fan then start and the liquid line solenoid energizes (opens) if
the controller calls for cooling.
•
The R-23 compressor starts 30 seconds later.
•
Unit operates in cool until the controlling sensor reaches 1.0 C (1.8 F) below setpoint on initial pull
down.
•
Controller turns ON the In-range LED when the controlling sensor temperature reaches 1.5 C (2.7 F)
above setpoint on initial pull down.
A.
Cool: Compressors operate a minimum of 15 minutes after startup to
prevent rapid cycling between Cool and Null modes.
1.
Decrease Temperature
B.
Null: Compressors are OFF a minimum of 10 minutes to prevent rapid
cycling between Cool and Null modes.
2.
Setpoint
C.
In-Range
3.
Increasing Temperature
Figure 19: Frozen Load Control Sequence (Setpoints at -10 C [14 F] and Below)
Содержание Thermo King CRR DF MPC2000
Страница 5: ...4 ...
Страница 11: ...List of Figures 10 ...
Страница 13: ...Introduction 12 ...
Страница 19: ...Safety Precautions 18 ...
Страница 21: ...Service Guide 20 ...
Страница 47: ...Unit Description 46 ...
Страница 97: ...Microprocessor Controller 96 ...
Страница 101: ...Electrical Maintenance 100 ...
Страница 141: ...Structural Accessory Maintenance 140 ...
Страница 147: ...Refrigeration System Diagnosis 146 ...
Страница 149: ...Electrical Refrigeration and Controller Menu Flow Diagrams 148 This page intentionally left blank ...
Страница 150: ...149 CRR DF MPC2000 Controller Diagram ...
Страница 151: ...150 CRR DF MPC2000 Main Relay Board Electrical Diagram ...
Страница 152: ...151 CRR DF MPC2000 Unit Wiring Schematic Low Speed Winding ...
Страница 153: ...152 CRR DF MP3000A Controller Diagram ...
Страница 154: ...153 CRR DF MP3000A Main Relay Board Electrical Diagram ...
Страница 155: ...154 CRR DF MP3000A Unit Wiring Schematic Low Speed Winding ...
Страница 157: ...156 CRR DF Refrigeration System Components Page 2 of 2 ...
Страница 159: ...158 CRR DF Off Cycle Standby Flow and Pressure Diagram Page 2 of 2 CRR DF Off Cycle Standby Flow and Pressure Diagram ...
Страница 161: ...160 CRR DF Full Cool Flow and Pressure Diagram Page 2 of 2 ...
Страница 163: ...162 CRR DR Evacuation Station and Unit Connections Page 2 of 2 ...