Figure 3-16 Pipe anti-freezing solution
(1) Water seal
(2) Electric heating belt
(3) Water refill pipe
(4) Drainpipe (connected to the utility
drainpipes)
(5) Soil
Figure 3-17 Requirement for wrapping the electric heating belt
NO TICE
● The temperature control switch is integrated with the electric heating belt. The
electric heating belt needs to be coiled evenly on the drainpipe and water refill
pipe during onsite construction. The temperature control switch is installed on
the post inside the maintenance door.
● Wrap the electric heating belt and then wrap the thermal insulation foam.
Ensure that the thermal insulation foam covers the temperature control switch
and temperature sensor probe. The thermal insulation foam must withstand a
temperature above 200°C.
3.3.6 Removing Transport Fasteners and Desiccant Bags
Procedure
Step 1 Remove the maintenance door of the compressor and take out the desiccant bags
from the compressor.
Step 2 Open the electric control box and take out the desiccant bag from the box.
FusionCol8000-E240 Modular Indirect Evaporative
Cooling System
User Manual
3 System Installation (Building Scenario)
Issue 02 (2021-04-15)
Copyright © Huawei Technologies Co., Ltd.