Figure 3-5 Concrete platforms for combined units (unit: mm)
(1) FusionCol8000-E
(2) Concrete platform
Step 2 Determine the reference points for installing the device on the concrete platforms.
Mark the reference points using a marker.
Step 3 Mark the positions of the four corner fittings using an ink fountain and long
leather measuring tape.
NO TICE
When marking the mounting positions for corner fittings, ensure that the four
lines form a rectangle.
Step 4 Adjust the device in the required direction, connect the steel hoisting ropes, and
hoist the device onto the concrete platforms.
NO TICE
When hoisting a device, ensure that the four corner fittings of the device are
aligned with the marked mounting positions for corner fittings on the concrete
platforms.