Step 3 Open the outdoor intake air filter and take out the desiccant bag from the
outdoor air intake compartment.
Step 4 Open the maintenance door and water barrier of the spray pump, and take out
the two desiccant bags from the spray pump compartment.
Step 5 Loosen the three transport fixing bolts of the compressor using a 13# solid wrench
and remove the sheet metal fasteners.
Figure 3-18 Removing sheet metal fasteners from the compressor
NO TE
● Do not remove the bolts.
● Keep the removed sheet metal fasteners properly for future transportation.
Step 6 Tighten the bolts on the compressor again to a torque of 12 N·m.
Step 7 Install the adjustable side panels for the compressor.
----End
3.4 Installing Cables
3.4.1 Precautions
●
Connections of all power cables, control cables, and ground cables must
comply with local electrical regulations, and the cable specifications should
comply with local cabling specifications.
●
For details about the maximum current, see the device nameplate.
●
Check that the input voltage and frequency of the primary power supply meet
the requirements.
●
Only trained and qualified personnel are allowed to connect cables.
●
Before connecting cables, use a multimeter to measure the input voltage and
ensure that the power supply is disconnected.
●
All smart cooling products must be securely grounded before being powered
on.
FusionCol8000-E240 Modular Indirect Evaporative
Cooling System
User Manual
3 System Installation (Building Scenario)
Issue 02 (2021-04-15)
Copyright © Huawei Technologies Co., Ltd.
48