Maintenance and care
multi N/C 2100S (duo, pharma)
80
}
Connect the lower end of the combustion tube and the inlet of the con-
densation coil via the spherical joint connection (1).
}
Secure the spherical joint connection with the forked clamp (2). Tighten
the knurled head screw (3) hand-tight.
}
Close the side wall.
– Connect the protective grounding to the left side wall.
– Slightly tighten the screws first on the bottom side and then on the
top side. Tighten the screws in turns.
}
Open the gas supply. Connect the power plug with the socket and switch
on the analyzer via the main switch.
}
Check the system for leaks.
ü
The analyzer is ready for operation again.
6.8
Removing and installing the combustion furnace
6.8.1
Removing the combustion furnace
CAUTION
Risk of burns at the hot furnace
¡
Switch off the device and allow it to cool before performing maintenance.
}
Switch off the analyzer via the main switch. Disconnect the power plug
from the socket. Shut off the gas supply on the pressure reducer in the
laboratory.
}
Open the left side wall of the analyzer. Push the accessory modules to the
side if necessary. Do not kink any connection hoses.
– Unscrew the four attachment screws. The screws are captive and re-
main attached to the wall.
– Remove the protective grounding. Set the side wall aside safely.
}
Remove the top cover.
}
Remove the combustion tube.
}
Remove the TIC condensate container and the condensation coil.
}
Pull the plug-in connector for the combustion furnace out of its socket.