Installation and Start-Up
Handling the Installation report
20
The manufacturer of this product requires information and the legislator demands proof
that a system delivered free of defects from the factory continues to possess the required
and certified quality properties after installation, start-up and putting-into-operation,
(also called: Assembly, Installation, Adjustment and Testing, abbreviated as: AIAT).
It is, therefore, absolutely necessary that the Installation report with the installation and
start-up data is sent without delay after completion of work to the address stated on the
installation report.
You will find the report in the system folder. The Installation report has to be handed over
to the responsible project manager (PM), who has to make sure that it will be sent to the
address, or fax number, printed on it. It is not foreseen to hand over this Installation report
to the customer.