Outdoor Unit
B - 6
2. Specification
SGP-E120J2GU2
Model
External dimensions (mm)
Hei
ght
2,253
W
idth
1,735
Dept
h
1,000(+106)
Weight (kg)
950
Performance (kW)
Cooling
capacity
35.5
Heating capacity
(Standard)
42.5
Heating capacity
(low temperature)
42.5
Power supply
220 ~ 240V
Electrical characteristics 50Hz
Operating
current(A)
5.2
Power consumption
(kW)
1.07
Cooling
(230V)
Power factor (%)
94
Operating
current(A)
5.4
Power consumption
(kW)
1.15
Heating
(230V)
Power factor (%)
94
Start up current (A)
30
Fuel consumption (kW) G/C
C
ooling
27.3/30.4
Heating
(standard)
29.6/33.5
Heating
(low temperature)
33.9/40.4
Compressor
Cooling oil volume (L)
4.1(HP-9)
Crank case heater (W)
30
Engine
Displacement(L)
2.472
Rated output(kW)
15.0
Type
Sanyo Genuine AP D-125
Lubricating oil Quantity
(L)
50
Starter motor
DC12V×2.2kW
Starter type
AC/DC conversion type
DC starter
Engine cooling water
Quantity(L)
27
Concentration, freezing
50V/V%, -35
ºC
Cooling water pump rated
output(W)
160
Refrigerant×Quantity(kg)
HFC[R407C]×12
Air
intake
Front and rear
Air outlet
Top
Piping
Refrigerant gas tube
31.75(brazed)
Refrigerant liquid tube
15.88(brazed)
Fuel gas port
R3/4(male screw)
Exhaust gas drain port
diameter(mm)
27 rubber hose
Operating noise dB(A)
57
Blower
Blower type
Propeller fan×2
Rated air volume (m
3
/min)
300
Rated output (kW)
0.45
Heater for drain filter (W)
60
Heater for cooling waterA
Coolingwater
heater(W)
250
Paint color (Munsell code)
Silky shade (1Y8.5/0.5)
Heating(low temperature)
Less than 20ºCDB, 15ºCWB
27ºCDB, 19ºCWB
20ºCDB
2ºCDB, 1ºCWB
7ºCDB, 1ºCWB
35ºCDB
Operating condition
Cooling
Heating(standard)
Indoor air intake temperature
Outdoor air intake temperature
2. The value of cooling power consumption indicates the electrical power consumed during cooling overload operation when Indoor air intake
temperature is 32ºCDB/23ºCWB, and Outdoor air intake temperature is 43ºCDB.
3. The operating noise was measured at the position of 1.5 meter from the ground and 1 meter from the front of the unit. However, in an actual
installation there are various additional conditions, and normally the noise level is higher than the indicated value.
4. Under fuel consumption, G indicates 100% propane, with a calorific value of 37.78MJ/NM
3
+5%, and C indicates other gas.
5. The values shown in the table are for 50Hz.
6. The specification is subject to change without notice, due to improvements etc.
Notes
1. The cooling capacity and heating capacity described in the tables are the values when the unit operates under the test condition of JIS B 8627
Summary of Contents for SGP-E120J2GU2
Page 49: ...Design D 5 2 Operating temperature ranges for heating and cooling Cooling Heating ...
Page 87: ...Design D 43 8 Salt resistant specification ...
Page 109: ...Construction E 22 4 Outdoor unit installation and construction ...
Page 110: ...Construction E 23 4 Outdoor unit installation and construction ...
Page 111: ...Construction E 24 4 Outdoor unit installation and construction ...
Page 112: ...Construction E 25 4 Outdoor unit installation and construction ...
Page 113: ...Construction E 26 4 Outdoor unit installation and construction ...
Page 114: ...Construction E 27 4 Outdoor unit installation and construction ...
Page 115: ...Construction E 28 4 Outdoor unit installation and construction ...
Page 116: ...Construction E 29 4 Outdoor unit installation and construction ...
Page 117: ...Construction E 30 4 Outdoor unit installation and construction ...
Page 118: ...Construction E 31 4 Outdoor unit installation and construction ...
Page 119: ...Construction E 32 4 Outdoor unit installation and construction ...
Page 120: ...Construction E 33 4 Outdoor unit installation and construction ...
Page 121: ...Construction E 34 4 Outdoor unit installation and construction ...
Page 122: ...Construction E 35 4 Outdoor unit installation and construction ...
Page 123: ...Construction E 36 4 Outdoor unit installation and construction ...
Page 124: ...Construction E 37 4 Outdoor unit installation and construction ...
Page 127: ...Construction E 40 5 Commissioning ...
Page 128: ...Construction E 41 5 Commissioning ...
Page 129: ...Construction E 42 5 Commissioning ...
Page 130: ...Construction E 43 5 Commissioning ...
Page 131: ...Construction E 44 5 Commissioning ...
Page 132: ...Construction E 45 5 Commissioning ...
Page 133: ...Construction E 46 5 Commissioning ...
Page 134: ...Construction E 47 5 Commissioning ...
Page 135: ...Construction E 48 5 Commissioning ...
Page 136: ...Construction E 49 5 Commissioning ...
Page 137: ...Construction E 50 5 Commissioning ...
Page 138: ...Construction E 51 5 Commissioning ...
Page 139: ...Construction E 52 5 Commissioning ...
Page 140: ...Construction E 53 5 Commissioning ...
Page 141: ...Construction E 54 5 Commissioning ...
Page 142: ...Construction E 55 5 Commissioning ...
Page 143: ...Separately Contents 1 Parts for the outdoor unit 1 Exhaust extension kit F 2 F 1 ...
Page 150: ...Periodicinspection G 3 1 Periodic maintenance contract 70 90 Type 120 150 190 Type ...
Page 155: ...Water heat exchange unit H 5 3 External view ...
Page 158: ...Water heat exchange unit H 8 4 Specification 2 External dimension diagram ...
Page 161: ...Water heat exchange unit H 11 4 Specification ...