INSTALLATION AND REMOVAL
HIGH REACH DEMOLITION MANUAL
7-40
Dig Boom Work Equipment Flow Settings
7
With dig boom work equipment fitted, adjust the flow valves to the
following settings. To adjust the flow setting rotate the body until
dim t is achieved. After setting the flow valves check that the work
equipment is operating at a safe speed. If in doubt contact a
Komatsu dealer.
(1)
(2)
Flow Control Valve Settings
Ref
Location
Dimension (t)
1
Boom Cylinder
Boom Raise
15.5mm
Boom Lower
15.5mm
2
Boom 1
Link Cyl Bottom
15.5mm
Left Rotation
12mm
Right Rotation
12mm
Summary of Contents for PC350LC-8
Page 2: ......
Page 3: ...FOREWORD 11...
Page 12: ...PRODUCT INFORMATION FOREWORD 1 10 SERVICE METER LOCATION 1 On top of the machine monitor...
Page 278: ...TROUBLES AND ACTIONS OPERATION 3 214...
Page 366: ...MAINTENANCE PROCEDURE MAINTENANCE 4 88...
Page 367: ...SPECIFICATIONS 15...
Page 371: ...SPECIFICATIONS SPECIFICATIONS 5 5...
Page 372: ...SPECIFICATIONS SPECIFICATIONS 5 6...
Page 432: ...SUPER LONG FRONT BOOM AND ARM ATTACHMENTS AND OPTIONS 6 60...
Page 496: ...SPECIFICATIONS HIGH REACH DEMOLITION MANUAL 7 64...
Page 497: ...INDEX 18...
Page 498: ...INDEX 8 2...
Page 501: ...COLOPHON 18...