1
7
6
2
3
4
5
Item Description
1.
Baseplate
2.
Shims or wedges
3.
Grout
4.
Foundation
5.
Sleeve
6.
Dam
7.
Bolt
Figure 29: Pour grout into baseplate
6.
Fill the remainder of the baseplate with grout, and allow the grout to set for at least 48 hours.
1
5
4
2
3
Item Description
1.
Baseplate
2.
Grout
3.
Foundation
4.
Dam
5.
Bolt
Figure 30: Fill remainder of baseplate with grout
7.
Tighten the foundation bolts.
4.6 Piping checklists
4.6.1 General piping checklist
Precautions
WARNING:
•
Risk of premature failure. Casing deformation can result in misalignment and contact with
rotating parts, causing excess heat generation and sparks. Flange loads from the piping
4.6 Piping checklists
40
Model CV 3196 i-FRAME Installation, Operation, and Maintenance Manual