11-2
G60 Generator Protection System
GE Multilin
11.1 TESTING
11 COMMISSIONING
11
The desired delay time is the interval from the point the frequency crosses the set threshold to the point the element oper-
ates. Some test sets can measure only the time from the ramp start to element operation, necessitating the subtraction of
the pre-threshold ramp time from the reading. For example, with a ramp rate of 0.20 Hz/s, start the ramp 0.20 Hz before the
threshold and subtract 1 second from test set time reading of ramp start to relay operation.
Note that the G60 event records only show the “pickup delay” component, a definite time timer. This is exclusive of the time
taken by the frequency responding component to pickup.
The G60 oscillography can be used to measure the time between the calculated source frequency crossing the threshold
and element operation; however, this method omits the delay in the calculated source frequency. The security features of
the source frequency measurement algorithm result in the calculated frequency being delayed by 2 to 4 cycles (or longer
with noise on the input). In addition, oscillography resolution is 0.004 Hz, which at 0.20 Hz/s corresponds to a delay of
20 ms. The tracking frequency should not be used in timing measurements, as its algorithm involves phase locking, which
purposely sets its frequency high or low to allow the G60 sample clock to catch-up or wait as necessary to reach synchro-
nism with the power system.
Summary of Contents for G60 UR Series
Page 2: ......
Page 4: ......
Page 12: ...xii G60 Generator Protection System GE Multilin TABLE OF CONTENTS ...
Page 32: ...1 20 G60 Generator Protection System GE Multilin 1 5 USING THE RELAY 1 GETTING STARTED 1 ...
Page 132: ...4 30 G60 Generator Protection System GE Multilin 4 3 FACEPLATE INTERFACE 4 HUMAN INTERFACES 4 ...
Page 392: ...5 260 G60 Generator Protection System GE Multilin 5 10 TESTING 5 SETTINGS 5 ...
Page 418: ...6 26 G60 Generator Protection System GE Multilin 6 5 PRODUCT INFORMATION 6 ACTUAL VALUES 6 ...
Page 482: ...A 12 G60 Generator Protection System GE Multilin A 1 PARAMETER LISTS APPENDIXA A ...
Page 604: ...D 10 G60 Generator Protection System GE Multilin D 1 IEC 60870 5 104 APPENDIXD D ...
Page 616: ...E 12 G60 Generator Protection System GE Multilin E 2 DNP POINT LISTS APPENDIXE E ...
Page 634: ...x G60 Generator Protection System GE Multilin INDEX ...