6.5 Column valve C tests
Column valve C tests
The following Column valve C tests are available, for ÄKTA pure 25 and ÄKTA pure 150, respectively:
• Column valve V9-C test
• Column valve V9H-C test
Method description
The Column valve C test checks the functionality of Column valve C, labeled V9-C or V9H-C, and of the
integrated pressure sensors that measure pre-column and post-column pressure.
The method run takes approximately 1 minute.
Required configuration
A correctly installed Column valve C is required to run the test.
Required material
The following materials are required:
• Syringe, 25-30 ml
• Distilled water
• Ref 1 tubing, see Reference capillary, on page 426.
Prepare the test
Follow the instructions below to prepare the system before method start.
Action
Step
Connect the Ref 1 tubing between Column valve C ports 1A and 1B.
1
Make sure the Flow restrictor is inline.
2
Direct outlet tubing W to a waste container.
3
Place inlet tubing A1 into distilled water.
4
Prime the inlet A1 and purge the pump. See Section 5.4.1 System pumps, on page 162.
5
ÄKTA pure User Manual 29119969 AB
235
6 Performance tests
6.5 Column valve C tests
Summary of Contents for AKTApure
Page 1: ...ÄKTA pure User Manual ...
Page 2: ...Page intentionally left blank ...
Page 520: ...Page intentionally left blank ...
Page 521: ...Page intentionally left blank ...