4. Commissioning
4-15
Festo P.BE-SBO-Q-EN en 1602e
Note
If the network connection is interrupted, the device may
remain in “assigned status”. In this case, setting up a new
connection to the device is not possible.
This occurs when:
Ethernet connection lines are unplugged
The power supply to Ethernet network components
(e.g. switch) is disconnected
Deactivation of the network card in the PC due to energy-
saving mode.
Briefly disconnect the power supply to restart the
device.
Additional information can be found in the CheckKon Help,
e.g. regarding the basic functions Device connection, Device
names and Device control.
Summary of Contents for SBO***-Q Series
Page 2: ......
Page 19: ...System overview 1 1 Festo P BE SBO Q EN en 1602e Chapter 1 System overview...
Page 39: ...Mounting 2 1 Festo P BE SBO Q EN en 1602e Chapter 2 Mounting...
Page 47: ...Installation 3 1 Festo P BE SBO Q EN en 1602e Chapter 3 Installation...
Page 62: ...3 Installation 3 16 Festo P BE SBO Q EN en 1602e...
Page 63: ...Commissioning 4 1 Festo P BE SBO Q EN en 1602e Chapter 4 Commissioning...
Page 162: ...4 Commissioning 4 100 Festo P BE SBO Q EN en 1602e Fig 4 34 Structure of an imported data type...
Page 183: ...Technical appendix A 1 Festo P BE SBO Q EN en 1602e Appendix A Technical appendix...
Page 247: ...Index B 1 Festo P BE SBO Q EN en 1602e Appendix B Index...
Page 248: ...B Index B 2 Festo P BE SBO Q EN en 1602e Table of contents B Index B 1...