5.
Secure the ceramic cannula with the red screw cap.
6.
Check that the sealing cone, seals and screw cap have been
fitted to the pump hose.
7.
Screw the pump hose finger-tight onto the red screw cap.
NOTICE! The TIC reactor can get hot. Install the pump hose
so that it does not touch the hot reactor.
8.
Connect the measuring gas outlet (1) with hose no. 72 to
the top end of the cooling coil on the rear of the TIC solids
module.
9.
Slide the hose for the oxygen supply (no. 17) onto the re-
actor connection for the carrier gas (2).
NOTICE!
Always support the reactor with one hand when
attaching the hoses. With too much pressure on the gas
cylinder, the TIC reactor might fracture.
10.
Place the acid bottle (3) into a drip tray before the acid
pump.
11.
Feed the end of the pump hose through one of the open-
ings in the screw cap into the acid bottle.
Summary of Contents for Analytik Jena multi EA 4000
Page 1: ...Operating Manual multi EA 4000 Elementary analyzer C S and Cl solids analysis...
Page 50: ...Commissioning multi EA 4000 50 Figure 32 multi EA 4000 C S Hose diagram...
Page 52: ...Commissioning multi EA 4000 52 Figure 33 multi EA 4000 Cl Hose diagram...
Page 54: ...Commissioning multi EA 4000 54 Figure 34 multi EA C S Cl for C S measurements Hose diagrams...
Page 55: ...multi EA 4000 Commissioning 55 Figure 35 multi EA 4000 C S Cl for Cl measurements...
Page 57: ...multi EA 4000 Commissioning 57 Figure 36 Automatic TIC solids module Hose diagrams...
Page 58: ...Commissioning multi EA 4000 58 Figure 37 multi EA 4000 C S with automatic TIC solids module...
Page 61: ...multi EA 4000 Commissioning 61 Figure 39 multi EA 4000 C S Cl with man TIC solids module...