Test Operation
SiBE37-701_B
173
Test Operation
z
If the check operation was not performed at first installation, the malfunction code “U3” will
be displayed in the remote controller. Perform the check operation following
.
3. Checks After Test Run
Perform the following checks after the test run is complete.
z
Record the contents of field setting.
→
Record them on the accessory “REQUEST FOR THE INDICATION” label.
And attach the label on the back side of the front panel.
z
Record the installation date.
→
Record the installation date on the accessory “REQUEST FOR THE INDICATION” label
in accordance with the IEC60335-2-40.
And attach the label on the back side of the front panel.
Note:
After the test run, when handing the unit over to the customer, make sure the EL.COMPO.BOX
lid, the inspection door, and the unit casing are all attached.
Summary of Contents for REYQ8-48PY1B
Page 1: ...Service Manual REYQ8 48PY1B R 410A Heat Recovery 50Hz SiBE37 701_B ...
Page 456: ...Piping Installation Point SiBE37 701_B 445 Appendix ...
Page 460: ...Example of connection SiBE37 701_B 449 Appendix ...
Page 476: ...Revision History Date News No Contents 2010 9 10 M 10011 Correction of service manual ...