Test Operation
SiENBE28-901
68
Air Cooled Refrigeration Condensing Unit
Note:
After knocking out the holes, we recommend you remove burrs in the knock holes and paint
the edges and areas around the edges using the repair paint.
5.3.3 Checking of Device and Installation Conditions
Be sure to check the followings.
<For those doing electrical work>
1.
Make sure there is no faulty power wiring or loosing of a nut.
See “
5.2.1 Procedure for Power Supply Wiring
”.
2.
Has the insulation of the main power circuit deteriorated?
Measure the insulation and check the insulation is above regular value in accordance with
relevant local and national regulations.
<For those doing pipe work>
1.
Make sure piping size is correct.
See “
5.1.2 Selection of Piping Material
”.
2.
Make sure insulation work is done.
See “
5.3.2 Thermal Insulation Work
”.
3.
Make sure there is no faulty refrigerant piping.
See “
5.1. REFRIGERANT PIPING
”.
Liquid side
shutoff valve
Gas side
shutoff valve
Indoor/Outdoor
interunit piping
Coking, etc.
Insulation material
Piping lead-out
hole lid
Open a knock
hole at
Block
Gas side piping
Liquid side piping