■ Control Description
In horizontal scanning direction, sensor level of each original detection position is measured by moving the Scanner Unit to the
detection position shown in the figure in relation to the original setting position. The size in the vertical scanning direction is
determined by using the Original Size Sensor (AB) and Original Size Sensor (Inch).
LTRR
STMT
LTR
LGL
279.4×431.8mm
(11"×17")
Original Size Sensor (Inch)
Inch type
STMTR
CCD original detection position
Original detection
position 1
Original detection
position 2
Original detection
position 3
Original Size Sensor (AB)
B5
A5
A4
B5R
A4R
A5R
B4
A3
K8
K16
AB type
CCD original detection position
Original detection
position 1
Original detection
position 2
Original detection
position 3
Original detection
position 4
Original detection position 5
Original detection position 6
Dust Detection Control
■ Overview
When reading an original, original reading position is changed according to the presence/absence of dust on the Stream Reading
Glass or the Guide Plate of the ADF (on the Platen Roller in case of the reverse model), or image correction is performed to
prevent the dust to be printed on an image. This control is performed only when the ADF is being used and has been closed.
Control timing
Dust evasion control
• At job completion
• At the start of a job (only when one of the following conditions is met)
• At the start of the first job after power ON or recovery from sleep mode
• At the start of the first job after a message prompting cleaning of dust is displayed and then the ADF is opened and then
closed
• At the start of a job when dust evasion control performed at the end of the previous job failed to finish normally
Image correction control
• At paper interval (after each sheet is read)
Main power
switch ON
Start key
ON
Dust detection
control
STBY
WMUP
1st
SCAN
2nd
SCAN
Dust detection
control
Dust detection
control
Control description
Dust evasion control
• At job completion
The Reading Sensor detects presence/absence of dust at the reading position A, B, and C in that order, and the position
where dust is least present becomes the reading position for the next job.
• When a job starts
Like the time of completion of a job, presence/absence of dust is detected at all positions (A, B, and C in that order).
The position where dust is least present is used as the reading position and reading starts.
2. Technology
41
Summary of Contents for imageRUNNER ADVANCE C3500 III Series
Page 1: ...Revision 2 1 imageRUNNER ADVANCE C3500 III Series Servie Manual ...
Page 23: ...Safety Precautions Laser 2 Power Supply Lithium Battery 3 Toner Safety 4 Notes on works 4 ...
Page 28: ...Product Overview 1 Product Lineup 7 Specifications 11 Parts Name 34 ...
Page 153: ...Periodical Service 3 Consumable Parts List 132 Cleaning Parts 136 ...
Page 158: ...Cleaning Parts 15 9 14 13 8 4 16 17 5 3 6 7 1 2 12 10 11 15 16 3 Periodical Service 136 ...
Page 211: ...2 Remove the HDD Unit 1 3 Hooks 2 1 Screw 3 1x 2 2 3 4 Parts Replacement and Cleaning 189 ...
Page 249: ...2 3 1x 4 Parts Replacement and Cleaning 227 ...
Page 306: ...Troubleshooting 6 Initial Check 285 Test Print 286 Troubleshooting Items 291 Debug Log 304 ...
Page 345: ...Error Jam Alarm 7 Outline 324 Error Code 328 Error Code FAX 466 Alarm Code 469 Jam Code 517 ...
Page 1029: ...1 2 2x 3 4 NOTE The removed CR BOX Upper Unit will be used in step 14 9 Installation 1007 ...
Page 1050: ...Installation Procedure Installing the Equipment 1 2 3 9 Installation 1028 ...
Page 1052: ...8 Turn ON the main power switch 9 Installation 1030 ...
Page 1063: ...2 2x 1x 3 1x 1x 1x 4 1x 1x NOTE The removed screw will be used in step 5 9 Installation 1041 ...
Page 1088: ...4 6x 5 4x 6 7 NOTE Do not close the Wire Saddle 1x 8 9 Installation 1066 ...
Page 1091: ...14 15 16 17 2x 18 9 Installation 1069 ...
Page 1104: ...2 2x 3 Connect the power plug to the outlet 4 Turn ON the power switch 9 Installation 1082 ...
Page 1112: ...When Installing the USB Keyboard 1 9 Installation 1090 ...
Page 1114: ...Installation Procedure Removing the Covers 1 2x 2 1x 3 2x 9 Installation 1092 ...
Page 1115: ... Installing the Removable HDD Kit 1 2 3x 4x 9 Installation 1093 ...
Page 1119: ...11 12 1x 13 NOTE Use the screw removed in step 3 1x 9 Installation 1097 ...
Page 1120: ...14 3x 4x Installing the Covers 1 2 2x 3 1x 9 Installation 1098 ...
Page 1123: ...Installation Procedure Removing the Covers 1 2x 2 1x 3 2x 9 Installation 1101 ...
Page 1127: ...8 3x 4x Installing the Covers 1 2x 2 1x 9 Installation 1105 ...
Page 1134: ...2 On the screen shown below press Change and then Detailed Settings 3 9 Installation 1112 ...
Page 1140: ...Installation procedure Remove the Control Panel 1 2 2x 3 4 2x 5 2x 9 Installation 1118 ...
Page 1141: ...6 2x 7 4x 8 3x 9 10 9 Installation 1119 ...
Page 1142: ...11 12 6x 13 2x 14 9 Installation 1120 ...
Page 1143: ... Installing the NFC Kit 1 2 2x 3 1x TP M3x4 4 1x 9 Installation 1121 ...
Page 1144: ... Installing the Control Panel 1 2 2x 3 6x 4 9 Installation 1122 ...
Page 1145: ...5 6 3x 7 4x 8 2x 9 10 2x 9 Installation 1123 ...
Page 1146: ...11 2x 12 13 2x 14 9 Installation 1124 ...
Page 1154: ...14 4x Installing the Relay PCB 1 1x 1x TP M3x6 1x 2 1x 1x 9 Installation 1132 ...
Page 1155: ...3 4 2x 3x 5 4x 6 9 Installation 1133 ...
Page 1162: ... Installing the Relay PCB 1 1x 1x TP M3x6 1x 2 1x 1x 9 Installation 1140 ...
Page 1163: ...3 4 2x 3x 5 4x 9 Installation 1141 ...
Page 1180: ...6 1x 7 8 5x M3x6 9 Installation 1158 ...
Page 1200: ...2 3 2x 4 1x 9 Installation 1178 ...