Refer to the following figure when connecting marker components. Keep the following points in mind
when connecting the components.
•
Do not share the power supply with other large equipment.
•
Avoid bundling connecting cables or remote control cables with other power cables. The resulting
electromagnetic noise may cause malfunctions.
•
Be sure to connect the peltier control connecting cable's grounding line (green) to the specified
positions (shown in the following figure) on the backs of the Head Unit and the Control Unit.
•
Connect the power cable to the power supply input receptacle.
•
When using the power supply conversion plug, be sure to connect the grounding cable.
•
To prevent damage, when bending the fiber, make sure the bending radius is at least 150 mm.
*1 The cable parts except for the connector parts of scanner control connecting cable, head control
connecting cable, peltier control connecting cable, and RF connecting cable are bundled and
covered with the shield tube.
*2 The optical fiber and the RF connecting cable cannot be disconnected from the Head Unit and the
Control Unit.
6.2 Connections
・
This work must be done only by qualified electricians.
・
The required power supply is as follows: single-phase 100 V AC to 120 V AC with a
capacity of at least 15 A, or 200 V AC to 240 V AC with a capacity of at least 7 A.
Single-phase 100V-120V
Capacity: 15A or more
or
Single-phase 200V-240V
Capacity: 7A or more
Power Cable
RF Connecting
Cable*1*2
Computer
Control Unit, Back
Head Unit, Back
Head Control
Connecting Cable*1
Optical Fiber*2
LAN Cable
Peltier Control
Connecting Cable*1
Grounding Wire
Avoid bending the fiber so the bending
radius is less than 150 mm.
Scanner Control
Connecting Cable*1
HDMI Cable (option)