FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
5 Installing the Cabinet
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
73
Figure 5-12
Installing a ground bar
----End
5.4.3 (Optional) Installing the Vertical Ground Bar
Context
The BOM number for the vertical ground bar is 21241363.
Procedure
Step 1
Open the rear cabinet door, and secure the ground bar to the right rack rail by installing four
M4 screws respectively at the 04 U, 14 U, 29 U, and 39 U positions. Note that a screw should
be secured to the middle tapped hole of each U.