FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
C Installation Verification
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
239
No.
Check Item
Check Result
maintenance and capacity expansion.
6
All labels at the cable ends are clear.
□ Compliant □ Incompliant
7
Excess sections of cable ties are neatly cut.
□ Compliant □ Incompliant
8
There is no unnecessary adhesive tape or cable tie
on cables.
□ Compliant □ Incompliant
9
All components are properly installed and no
component is left onsite.
□ Compliant □ Incompliant
Electric Installation Checklist
No.
Check Item
Check Result
1
All ground cables are copper cables with diameters
meeting the requirements. No switch or fuse is
installed at the middle of a ground cable, and no
short-circuit occurs.
□ Compliant □ Incompliant
2
Ground cables, AC input power cables, and
internal cables are connected in accordance with
the circuit diagram and screws are secured. No
short-circuit occurs on power inputs or outputs.
□ Compliant □ Incompliant
3
Power cables and ground cables are not coiled and
extra parts are cut off.
□ Compliant □ Incompliant
4
Lugs for power cables and protective ground
cables are soldered or crimped securely.
□ Compliant □ Incompliant
5
Power cables and ground cables are routed and
bundled separately from other cables.
□ Compliant □ Incompliant
6
Batteries are free from damage, cracks, and bulges. □ Compliant □ Incompliant
7
Batteries are neat and do not leak electrolyte.
□ Compliant □ Incompliant
8
Wiring terminals of batteries are free from
damage, break, and acid leakage.
□ Compliant □ Incompliant
9
Battery safety valves are intact, without leakages.
□ Compliant □ Incompliant
10
Battery cables are correctly connected, and the
terminal voltages of battery strings are normal.
□ Compliant □ Incompliant
11
DIP switches on devices are correctly set.
□ Compliant □ Incompliant