1.1 Transportation and Placing Precautions
Air Conditioner Transportation Precautions
Only trained personnel are allowed to move the cabinet. Use a pallet truck to transport
the cabinet secured to a wooden support to the installation position. Insert the forks of
the pallet truck in the middle position to ensure balance.
Choose railways, sea, or a road with good condition during transportation. No excessive
tilt or jolt is allowed during the transportation, and the maximum tolerance of the tilting
angle during loading and unloading is 15°, as shown in
To prevent the cabinet from falling over, secure it to a pallet truck using ropes before
moving it.
To prevent shocks or falls, move the cabinet gently.
Move the equipment close to the installation site before unpacking. Unpack the
equipment with caution to avoid scratching or bumping. Take down the equipment from
the pallet only immediately before installation.
Figure 1-1
Transportation gradient