FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
A Appendix
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
212
Sealing Plate
BOM Number
600 mm wide, 2000 mm high sealing plate
21500718
800 mm wide, 2000 mm high sealing plate
21500720
300 mm wide, 2200 mm high sealing plate
21500939
600 mm wide, 2200 mm high sealing plate
21500940
800 mm wide, 2200 mm high sealing plate
21500941
Procedure
Step 1
Determine the positions of sealing plates, directions of the conca ve sides of sealing plates, and
the area covered by the adjustable skylight based on the actual installation environment and
the description in
Step 2
Install the sealing plates near the aisle.
Install the sealing plates near the aisle containment first, and then the sealing plates near the smart
module exterior.
1.
Secure the two sealing plates using three M6 screws and nuts.
2.
Place the connected sealing plates at the specified installation position, facing the correct
direction.
3.
Drill four holes in the floor through the four holes at the bottom of the sealing plate using
a hammer drill with a 15 mm drill bit. Secure the sealing plate to the floor using four
plastic expansion bolts labeled DKBA44091028 and four washers.
If drilling holes in the ESD floor is not supported onsite, use four ST4.8x25 self-drilling tapping screws
and washers for securing.