FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
4 Hardware Installation Preparations
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
43
Name
Specifications
Quantit
y
Remarks
External
circuit
breaker
NetCol
5000-
C030H
6
NetCol
5000-
C030H
7
without
heating
and
humidif
ication
Minimum specifications for the
active and standby routes: AC
circuit breaker, 230/400 V, 10 A,
2P, C feature
1 PCS
Engineering
purchasing
NetCol500
0-C030H7
with
heating
and
humidificat
ion
Minimum specifications for the
common power cable: AC circuit
breaker, 230/400 V, 40 A, 2P, C
feature
1 PCS
Engineering
purchasing
Minimum specifications for the
backup power cable: AC circuit
breaker, 230/400 V, 10 A, 2P, C
feature
1 PCS
Engineering
purchasing
Teamwork networking
and monitoring cable
10 m
1 PCS
Standard
configuratio
n; delivered
with the
product
PE cable (outside the
cabinet)
≥ 6 mm
2
1 PCS
Engineering
purchasing
4.2.2 Checking the Air Pressure
Context
The device has been injected with 0.3–0.5 MPa nitrogen before delivery. Check the air
pressure for Nitrogen leakage.
Procedure
Step 1
Open the rear door.
Step 2
Remove the air filters.
1.
Unfasten the eight rotating check plates in the upper and lower positions of the air filters,
as shown in