FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
1 Installation Preparations
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3
Step 5
Sign on the
Packing List
with the customer after verifying that all required items are
delivered.
Step 6
Store the items properly.
----End
Follow-up Procedure
Put the items to be installed immediately onto an ESD surface, such as a polyethylene (PE)
bag or an expandable polyethylene (EPE) foam. Pack the items not to be installed
immediately with their original packing materials. Put them in a dry and cool environment
without exposure to sunlight or electromagnetic radiation.
1.3 Installation Environment Requirements
Ensure that the installation environment meets the requirements before installation.
Table 1-1
Installation environment checklist
Check Item
Requirement
Check Result
Floor bearing
capacity
Standard live load of the equipment
room: 8–12 kN/m
2
(If the battery
cabinet is contained in the module,
use the standard live load of the
equipment room as a reference.)
Suspended load of the equipment
room: 1.2 kN/m
2
Standard live load of the UPS room:
8–10 kN/m
2
Standard live load of the battery
room: 16 kN/m
2
Standard live load of the monitoring
center: 6 kN/m
2
□ Compliant □
Incompliant
Equipment room net
height
See the field requirements for details.
□ Compliant □
Incompliant
Device passage and
door height and
width
Height ≥ 2.2 m and width ≥ 1.2 m
□ Compliant □
Incompliant
Floor levelness
Allowed deviation: 3 mm/2000 mm
□ Compliant □
Incompliant
Elevator
Elevator bearing capacity > 1.5 t
Inner dimensions: height > 2.4 m or
depth > 2.7 m
□ Compliant □
Incompliant
Cable tray
Preinstalled in the equipment room for
signal cables and power cables
□ Compliant □
Incompliant