FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
A Appendix
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
225
Step 2
Place the connected sealing plates at the specified installation position, facing the correct
direction.
Step 3
Secure the parallel plate obtained from the sealing plate fitting bag to the sealing plate using
M4 screws, and then secure the sealing plate to the cabinet.
Figure A-32
Installing the sealing plates away the aisle
(1) Column
----End
A.6 (Optional) Connecting Cables to Industrial
Connectors
to
show only the cable connection methods. The industrial connector
cable connections depend on the industrial connector type and wiring port silk screen.