FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
4 Hardware Installation Preparations
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
53
persons carry the equipment. Force-bearing area is shown in
. The other two hold
it to prevent tilting. Then install the side panel.
Exercise caution when moving the cabinet to prevent falling down.
Figure 4-36
Transport
----End
4.4 Adjusting the Baffle Plate for the Air Conditioner
Context
Perform the following procedure to change the position of the baffle plate if required.
Procedure
Step 1
Loosen the two screws shown by (1) in